« Neighborhood maps now available | Main | Illegal dumping in neighborhood parks »

October 30, 2007

Construction has started on the 29th to 34th Street Tunnel (archived content)

Construction will begin soon on the Shoal Creek Wastewater Improvements - 29th Street to 34th Street Tunnel. Construction will begin in August 2004 and is schduled to conclude in Summer 2006 (see invitation and project map - pdf file) . Bryker woods neighbors are invited to meet the contractor Thursday, August 5, 2004 6:00 to 7:30 P.M. Bryker Woods Elementary Cafeteria 3309 Kerbey Lane. Please RSVP to the ACWP Hotline 684-3204 (refreshments will be served). Click hear to learn more on the project! (pdf file)

Some deatils outilned for the Shoal Creek WW Improvements 29th Street, 32nd Street, 33rd Street/Churchill Drive/Seton

Install a new 12-inch wastewater line in 34th Street that will accommodate the expansion at Seton Hospital. Work will begin in spring 2004 at West 34th Street.
Replace existing sewers on 32nd Street, Churchill, 33rd Street. This includes creekbank improvements and reconstruction of the west trail pavement, and at the request of Parks and Recreation Department (PARD), it features construction of a new pedestrian creek crossing south of West 34th Street. Work will begin in summer 2004 and conclude in spring 2005.
Install an 8-inch wastewater line that serves the area west of Shoal Creek, south of 29th St. This improvement will enable the City to take the existing line out of the creek. The installation of this line will impact the existing creek-side trail, so the trail will be rebuilt with an improved long-life surface. At the request of PARD, the project will include construction of a new pedestrian creek crossing south of 29th Street. Work will begin in summer 2004 and conclude in spring 2005.
New manholes will be designed using new city guidance for creek manholes.
Old manholes to remain will be rehabilitated.
(for more information see official notice (PDF 252k) and latest project plan (PDF 150k)

Visit the ACWP website for the latest information and a complete overview!

TrackBack

TrackBack URL for this entry:
http://www.typepad.com/t/trackback/2653275/22903316

Listed below are links to weblogs that reference Construction has started on the 29th to 34th Street Tunnel (archived content):